Big progress happened to our Uchi today!
They started the frame for the stair's railing... we cannot wait until Monday to see our railing:
We also have our kitchen cabinets now - they are not quite done yet. We now can see how each our room will be painted and decorated. You can also see our fireplace:
Our second floor has trim already
Yesterday we said we didn't have any upgrades - but actually, the white trim is one of our upgrades to Uchi. I like the trim having the same color as our stairs and kitchen cabinets!
It looks nice, right? : )
All the second floor rooms have doors now - including the closet doors.
See we have a closet in the small bedroom now!
Also, doors to each of our rooms!
First floor:
Floors for hallways, laundry room, front foyer, bathroom, kitchen and dining room are DONE!
Frame for stairway railing is DONE! (No iron railing posts yet...)
Fireplace is DONE! Completely!
Kitchen cabinets are ALMOST DONE, except the one for our double ovens.
Second Floor:
Doors for rooms and closets are DONE!!
Trim is DONE!!!
Cabinets for bathrooms are installed! (No actual counter tops yet...)
Well, see you later, in our next update!